Thain Creek Culvert Replacement, North
Vancouver
Owner: City of North Vancouver
Consultant: Kerr Wood Leidal
Associates Ltd.
Description:
Construction of the Thain Creek replacement
concrete culvert, and open channel drainage and landscaping work, all
under strict environmental guidelines. |
|
|
|
|
|
|
Dollarton Highway,
North Vancouver
Owner:
District of North Vancouver
Consultant:
InterCAD Services Ltd.
Description:
Construction of 360m of trunk storm sewer, outfall structure,
shoreline works, 210m of watermain, erosion and sediment control and
related works. |
|
|
|
|
|
|
Cypress/Hollyburn Sewer Link, West
Vancouver
Owner: Ministry of Environment,
Lands & Parks
Consultant:
UMA Engineering Ltd.
Description:
Connection of a 200mm diameter sewer line in
a 10m vertical section. |
|
|
|
|
|
|
Dominion Avenue Pump Station, Port
Coquitlam
Owner:
City of Port Coquitlam
Consultant:
G.D. Hamilton Associates Consulting Ltd.
Description:
Installation of
a pump station and excavation
of a retention pond, to
accomodate the increased run-off
predicted
for an upcoming
development. |
|
|
|
|
|
|
Gulf View Wynd Storm Sewer Outfall &
Improvements, Delta
Owner:
The Corporation of Delta
Consultants:
Aplin & Martin Engineering Ltd.
Description:
Installation of a 450mm
diameter steel pipe for
a storm sewer between
the US and Canadian
borders. Installation of a 600m storm
outfall, a concrete
outfall structure, and a
storm and sanitary main.
Highlights included
descending 70m on a 50
plus degree slope and
the installation of a
concrete dissipation
chamber. Maximum
slope 87.33%. |
|
|
|
|
|
|
|
|
|
|
|