Lynn Valley Road Supply Main, North Vancouver
Owner:
Greater Vancouver
Regional District
Description:
Construction of seismic
upgrades for the Lynn Valley Road
supply
main and
pipe crossing
abutments. |
|
|
|
|
|
|
Camp Fircom Sewage Outfall,
Gambier Island
Owner:
Camp Fircom Society of the United Church of
Canada
Description:
Construction of a sewage outfall complete with
a marine section on Gambier Island. |
|
|
|
|
|
|
Capilano Golf and Country Club, West
Vancouver
Owner: Capilano Golf and
Country Club
Consultant: Kerr Wood Leidal Associates Ltd.
Description: Repair of approximately 15 locations of
the Hadden Creek rock
channel lining, including
all materials and all other related work, plus
replacement of the two
golf cart crossings at
the 12th fairway. |
|
|
|
|
|
|
Cariboo Dam Apron Repair, Burnaby
Owner: Greater Vancouver
Regional District
Description: Placement of concrete at the front of the Cariboo Dam
and installation of a tarp wall to isolate
the "concrete water"
from the rest of the
reservoir. |
|
|
|
|
|
|
Kinsmen Field Aluminum Bleacher, North
Vancouver
Owner: City of North Vancouver
Consultant: Habitat Systems Incorporated
Description: Coordinated the installation of a 610
person capacity aluminum
bleacher. |
|
|
|
|
|
|
Suicide Bend Shoreline Protection, West
Vancouver
Owner: District of West
Vancouver
Consultant: Hay & Company Consultants Inc.
Description: Performed erosion control work,
including excavation of
existing shoreline and
construction of
specified shoreline
protection works.
Restored localized areas
of bank degradation at
elevations above
shoreline protection
works. |
|
|
|
|
|
|
Refurbishing Dundarave Park Playground,
West Vancouver
Owner: District of West Vancouver
Description: Removal and replacement of outdated play
equipment, paths,
retaining walls,
landscaping and play
structures. |
|
|
|
|
|
|
Ansell Place Wastewater Treatment Plant
Outfall Rehabilitation,
West Vancouver
Owner: District of West
Vancouver
Consultant: Kerr Wood Leidal Associates Ltd.
Description: Construction of 2.5m outfall over the
West Vancouver
foreshore. |
|
|
|
|
|
|
Slope Stabilization, Parkside Lane,
North Vancouver
Owner: District of North
Vancouver
Consultant: OMNI Engineering Inc.
Description: Construction of an approximately 9m high lock block
wall with access only via the
beach foreshore. |
|
|
|
|
|
|
|
|
|
|
|
|